    Eni, TotalEnergies Approve Cyprus Cronos Gas Project for 2028 LNG Exports

    View of the island of Cyprus from space

    Cyprus’ first gas development will send offshore production through Egypt’s Zohr facilities and Damietta LNG terminal for export to European markets

    By Bosphorus News Energy Desk

    Eni and TotalEnergies have taken a final investment decision on the Cronos gas field, putting Cyprus' first offshore gas development on a path toward production in 2028 and LNG exports through Egypt.

    The companies each hold a 50 percent stake in Block 6, with Eni as operator. Output is expected to reach about 500 million cubic feet of gas per day, equivalent to roughly 2.8 million tonnes of LNG a year. Each company will market around 1.4 million tonnes annually.

    Discovered in 2022 and confirmed by the Cronos-2 appraisal well in 2024, the field lies in deep water about 185 kilometers southwest of Cyprus. It will be developed through four subsea production wells.

    The gas will travel through a new subsea pipeline to Egypt, where it will be processed using infrastructure linked to the Zohr field, liquefied at Damietta and exported primarily to European markets.

    Egypt route moves into development

    The project gives commercial force to the Cyprus-Egypt export framework agreed in 2025.

    That arrangement brought Cyprus, Egypt, Eni and TotalEnergies together around a model based on existing Egyptian infrastructure. It covers the movement of gas from Block 6, processing in Egypt, liquefaction at Damietta and the sale of the resulting LNG.

    The final investment decision turns that framework into a scheduled development project.

    The announced plan does not include a new LNG export terminal in Cyprus. The partners instead chose to connect Cronos to facilities already operating in Egypt, shortening the timetable and limiting the amount of new infrastructure required.

    TotalEnergies has also said the model should lower the project's carbon intensity.

    The choice strengthens Egypt's position as a gas-processing and LNG export center in the Eastern Mediterranean. It also shows which regional export model has, for now, moved furthest toward execution.

    Plans for a new Cypriot LNG plant or a long offshore pipeline to Europe have remained under discussion for years. Cronos will use a shorter link to Egypt and capacity that already exists.

    TotalEnergies Chairman and CEO Patrick Pouyanné said the project would open a new Mediterranean gas route, support European energy security and contribute to an Eastern Mediterranean gas hub centered on Egyptian infrastructure.

    Damietta secures new supply

    Cronos will provide Damietta with a new source of gas from outside Egypt. Eni said the project would support the restart of the LNG plant and restore structural LNG exports from the country.

    The company will market 1.4 million tonnes of LNG a year from Cronos as part of a wider plan to expand its global portfolio beyond 20 million tonnes annually by 2030.

    Damietta is central to the economics of the development. Connecting a deepwater field to existing processing and liquefaction facilities avoids the cost and delay of building an entirely new export chain.

    The same infrastructure could later serve other discoveries in Block 6. TotalEnergies has said additional resources may be appraised in future drilling campaigns and potentially tied back to the Cronos system.

    Cyprus moves closer to first production

    Cyprus has announced several offshore discoveries since exploration began, but none has entered commercial production.

    Aphrodite was discovered first, followed by Calypso and Cronos. The significance of the latest decision is therefore not another find, but the approval of a development plan and a route to market.

    The 2028 target will depend on detailed engineering, subsea construction, pipeline installation and work on the Egyptian side.

    The companies have not disclosed the total investment cost or a precise date for the first LNG cargo.

    Even so, the decision is the clearest commercial milestone yet for the island's offshore gas sector. It moves the partners into the project's execution phase and gives Cronos a timetable earlier discoveries lacked.

    It also provides a practical answer to a question that has shaped Eastern Mediterranean energy policy for more than a decade: how offshore gas from Cyprus can reach international buyers.

    For Cronos, the answer is Egypt.

    Turkish Cypriot side maintains objection

    The project also sits inside the island's unresolved political dispute.

    The Republic of Cyprus awards offshore licenses and signs energy agreements on the basis that it represents the internationally recognized state.

    The Turkish Cypriot side argues that hydrocarbon resources around the island belong equally to both communities and should not be developed through unilateral decisions.

    In an April statement on the Cyprus-Egypt hydrocarbon framework, the Turkish Cypriot Foreign Ministry said agreements reached without Turkish Cypriot consent ignored their equal rights and interests.

    The ministry said such arrangements had no validity for the Turkish Cypriot side and added that political, diplomatic and technical measures would continue in coordination with Türkiye.

    That statement preceded the Cronos investment decision and was not a direct response to this week's announcement. It nevertheless reflects the standing Turkish Cypriot position on offshore development.

    No new statement specifically addressing the Cronos decision had been identified from the Turkish Cypriot side or the Turkish government at the time of publication.

    Separate from Vasilikos

    Cronos is unrelated to the delayed LNG import project at Vasilikos.

    Vasilikos is intended to bring LNG into Cyprus for domestic power generation. Cronos is an export project under which offshore gas will be sent to Egypt, converted into LNG and sold abroad.

    The decision does not complete Cyprus' import infrastructure or resolve the problems surrounding Vasilikos, but it does settle the commercial route for Cronos.

    If the 2028 timetable holds, Cronos will become Cyprus' first gas development to enter commercial production, with Zohr and Damietta forming the backbone of a new LNG route to Europe.

    Sources: Eni, TotalEnergies, Turkish Cypriot Foreign Ministry, Bosphorus News reporting and review